Cianbro Eastern Manufacturing Facility

Home
City Council
Development
Online Services
Code Permits
New Items
Zero Sort Recycling
Bids-RFP-RFI
Commerce Park
Energy Project
Cianbro Facility
Calendars
City Departments
School Department
Stormwater Program
CDBG Housing Grant
City Ordinances
Tax Maps
Subscribe City E-List
Veterans Memorial
Land Use
Brewer Land Trust
General Information
Historical Society
City Phone Listing
Career Opportunities
Privacy Statement
Disclaimer

Cianbro’s Brewer plant makes parts for island ferry project

Wednesday, September 15, 2009

A large crane, pipe pile and precast concrete will leave the Eastern Manufacturing Facility today for a ferry repair project on Swans Island, company spokesman Alan Grover said Tuesday.

The crane will be used to build six new dolphins for the $4 million Maine State Ferry Service project that Pittsfield-based Cianbro Corp. has been hired to construct. A dolphin is a buoy, pile or cluster of piles for mooring a vessel.

The project, which will begin shortly after the materials arrive, is scheduled to be complete in mid-June 2010.

“Some preliminary work is already under way,” Grover said. “It’s basically demolition work. This is the beginning of the job.”

The Cianbro-made sections of precast concrete, which look like massive disks with six holes for the pipes, will be stacked upon each other and shored up with the pipe pile, which will be pounded into the ground around the island’s terminal.

“Together all of that forms the new nest where the ferry will nestle up to with the fender system to provide the buffer,” Grover said.

The ferry service to the island will not be interrupted, he said.

“We can’t impact ferry service; that’s part of our agreement,” Grover said.

Billy Polk, Cianbro’s project manager for the Swans Island project, said the company is hiring a number of local people.

“It’s nice to be able to put local people to work whenever possible,” he said.

A barge will carry the 140-foot crane and materials down the Penobscot River to the construction site.

“This is really the first time that we’ve done another project at that site,” Grover said of the Brewer Eastern Manufacturing Facility, which was built to construct refinery modules for a massive oil refinery expansion in Texas.

With the next load of modules scheduled to leave for the Motiva Port Arthur Refinery in early October, nearly 40 percent of the contracted 54 modules will be delivered, Grover said.

A copyright story from the Bangor Daily News, Wednesday, September 16, 2009 by Nok-Noi Ricker.

Animal Control, Assessing, Cemeteries, City Clerk, City Council, City Manager,
City Planner, Code Enforcement, Economic Development, Elections, Engineering,
Environmental ServicesFinance/Tax Office, Fire, Health Officer, Human Services, Landfill, Library, Parks & Recreation, Police, Public Works, Public Safety, Recycling Center, Sewer Utility Billing, Technology, Universal Waste, Water,
 Water Pollution Control Facility, Zero Sort Recycling

City of Brewer E-List
The City of Brewer invites you to
subscribe to our
E-List to stay informed of City news and events.

Brewer, Maine Map to Brewer
offers economic opportunity with its urban location and access to
an excellent highway network while maintaining its small town quality of life.

The City of Brewer, Maine is a service center community of approximately 9,000 residents on the Eastern bank of the Penobscot River. Brewer is an equal opportunity employer and service provider. For information on City projects and news, see www.brewerme.org

 MainePages.com

City of Brewer, 80 North Main Street, Brewer, Maine 04412
This is the official City of Brewer web site which was designed and is maintained by the City.
This web page was last modified: Friday, July 23, 2010.