Rig
readied for Penobscot dredging
Wednesday, July 23, 2008*
A large barge and crane Monday was moved into place in the Penobscot
River, just offshore of Cianbro’s new Eastern Manufacturing Facility,
and will be used to dredge the river to make a channel deep enough to
handle heavy barges, a company official said.
Prock Marine of Rockland has been hired to remove 11,000 to 12,000
cubic yards of earth from the riverbed, Tom Ruksznis, Cianbro project
manager for site development, said Tuesday.
"They’ve been hired to do two things," he said. "They’re going to do
the dredging that starts August 1 and they have been hired to install
two dolphins."
The dolphins are tie-down points for the barges and are constructed
by driving three massive steal pilings into the soil at the deep-water
bulkhead, he said.
Cianbro Corp., a Pittsfield construction company known around the
state and the nation, has a multimillion-dollar contract to construct 52
building modules — prefabricated, self-standing building skeletons — for
a refinery expansion project in Texas.
The frames of the first set of refinery modules now are visible at
the site. Once finished, they will be shipped out by barge and put
together on-site at the Motiva Port Arthur Refinery, which is in the
middle of a $7 billion expansion that will make the facility the largest
crude oil processing plant in North America.
Dredging the river was required to make room for the heavy barges
that will transport the building modules, which can be as tall as five
stories and weigh up to 1,200 tons.
"We excavated approximately 5,000 cubic yards last winter before the
February 28 deadline, and put it on the site" as fill, Ruksznis said.
Most of the January and February dredging was done from the riverbank
using two huge cranes. The newly excavated materials also will be reused
on the 41-acre riverfront locale, he said.
The break in the excavation was required to avoid a possible adverse
impact on native fish, including short-nosed sturgeon and Atlantic
salmon.
"We’ll have approximately 10 feet of water depth at low tide once
we’re done dredging," Ruksznis said. "Before we started last fall, there
was exposed soil at low tide at the corner where we put in the bulkhead.
It was 1 to 2 feet. Most of the dredged area is underwater all the
time."
Cianbro and its subcontractors have worked since fall to change the
defunct Eastern Fine Paper Co. mill site, which closed in 2004, into a
modular manufacturing facility.
"That’s [the dredging] really the only remaining work we have to do
for site development," Ruksznis said.
A copyright article from the Bangor
Daily News, July 23, 2008.
*The dredging
equipment is in place to start the work in the Penobscot River along the
former Eastern Fine Paper site. The work will start on August 1st to
deepen the water for the new Cianbro facility. (Bangor Daily News/Gabor
Degre) |