| Cianbro crews
began erecting Wednesday at the Eastern Manufacturing Facility
in Brewer the first of 52 construction modules that will become
part of an expanding Texas oil refinery. Using a crane to hoist the
25-foot steel beams, a crew of about 10 had assembled more than 60
percent of the first module’s initial phase by midafternoon, said Tom
Meunier, unit superintendent for Cianbro Corp. When complete in roughly
three weeks, the module will be 30 feet wide, 120 feet long and 50 feet
tall, he said.
Everything at the module site, from the large steel beams to buckets
of bolts, have bar codes that identify the product and its proper
location within the structure to ensure precision and a quality finished
product, Steve Foster, safety manager for Cianbro, said.
"Everything we have done up and to this point was to get to this —
the building," Foster said.
Cianbro, a Pittsfield-based construction company, was awarded a
multimillion-dollar, 15-month contract to build the modules as part of
Motiva Port Arthur Refinery’s $7 billion expansion in Texas. Once the
expansion is complete, the refinery will be North America’s largest
crude oil processing plant and the seventh largest in the world, Foster
said.
The steel beams arrived by truck at the Brewer site during the past
few weeks, Foster said. When the first modules are complete, they will
be shipped by barge to Texas. Cianbro began dredging a part of the
Penobscot River to make the channels deep enough to handle the barges
and the heavy loads. Dredging was halted at the end of February due to
permit requirements and will resume Aug. 1. The first modules erected in
Brewer are expected to depart for Texas by fall, Foster said.
For months, Cianbro has worked to transform the 41-acre site,
formerly home to the Eastern Fine Paper Co., into a manufacturing
facility. On Monday, about 100 Cianbro and subcontracted workers milled
about the site working on a variety of projects.
One crew worked exclusively on restoring and renovating a former mill
building to be used by Cianbro as administrative offices, Foster said.
The renovation should be completed within three weeks, he said.
Demolition of the mill’s old boiler house also began on Wednesday. That
work is being done by Massachusetts-based Costello Dismantling Co., Inc.
In total, Cianbro has 165 employees assigned to the module project,
which the company estimates eventually will employ 450, Foster said.
While many people have interviewed for jobs, some have not committed to
jobs with the company because the facility was not up and running, he
said.
Given today’s economy, many prospective employees do not want to
leave a construction job during prime season without signs that the
project will reach fruition, Meunier said. Now that steel is being
erected and people can watch the progress from across the river, Meunier
said he expects to see a new wave of applicants.
Thirty employees were training at the site on Wednesday, and the
company has a total of 90 to 100 trainees in facilities around the
state. Within a month-and-a-half to two months, Cianbro expects to bring
the trainees to the Brewer site to work alongside the company veterans
who have begun the assembly, Meunier said. Pipe fabrication will start
by the end of May, he said.
"I believe we are putting steel up a little earlier than expected,
but [we] will put up pipe a little later," Meunier said. "By late June
to July you’ll see a vast amount of activity."
A copyright story from the Bangor
Daily News, Thursday, April 24, 2008.
|